Aaron Concrete Contractors, LLC will construct the two lane roundabout project in phases. Construction is expected to begin in summer 2023 and be complete in fall 2023. Two lanes of traffic (one in each direction) will be open throughout construction.

​

PHASE 1

  • Prepare site for construction and set barricades

  • Utility coordination and relocation

​

PHASE 2

  • Construction of north side of roundabout

​

PHASE 3

  • Construction of south side of roundabout

​

PHASE 4

  • Final paving and landscaping

Hays County will continue to coordinate with property owners and the community throughout construction. Additional information will be provided as information becomes available. Sign up for updates to be notified as the construction moves forward.

FUNDING

Construction for the roundabout is funded utilizing available funds from the voter-approved 2016 Road Bond – Safety and Mobility Projects. Bonds typically include a list of projects but are not limited to those projects, and the funds can be used for other transportation projects.